Site status as at March 2026: As we move closer towards the final phases of construction, you will be hearing from us more often: monthly in fact. There’s a lot to cover off in this edition with some major milestones recently achieved. In this March update we provide:
- An overview of construction status across the site.
- An introduction to the fully staged Show Home.
- An update on timing of our titles and settlements.
- Information on Quality Assurance and Defecting.
- A wider sales update.
- An explanation of the next steps.
Construction Progress.
- Significant progress has been made across the development. Civil works are now complete, with just final finishing touches remaining.
- Vertical construction across Stage 1 (Groups A-E) is nearing completion, with most homes now at the final finishes phase (including painting, kitchen installation, and floor coverings). Several units are now complete, with the focus shifting toward final detailing and defecting to ensure a high-quality finish for handover.
- Stage 2 (Group H): First fix plumbing & electrical complete, continued gib stopping.
- Stage 3 (Group G): First fix plumbing & electrical complete, internal linings complete.
- Stage 4 (Group F): Framing complete, exterior cladding complete.
- Site-wide, the attention to detail is impressive, right down to the entry signage – a stunning addition is currently being fabricated for the Pendarves Street Entrance.
You can find the rest of the March 2026 update here